Transport & Installation of Ophir Wellhead Platform
Year: 2017 (Feb-April)
Location: Malaysia Activity: Transport and Installation |
Project Scope:
Transport and Installation of Ophir wellhead platform. The 1100Mt suction pile based jacket and 350Mt topside were fabricated at Muhibbah yard in period 2016/2017. The jacket was transported horizontally on a barge. Upon arrival the jacket was lifted by 3200Mt HLV Asian Hercules II, upended and installed within 2 days. Subsequently, the topside was transported on separate barge and installed by the AH2 straight after jacket installation.